Loft conversion and Refurbishment, Bates Road Brighton

Dec 15, 2018
1 min read
Updated: Apr 28

Day 7 - External tiles are removed from the rear section roof eaves and we've installed the second double timber lintel. A timber plate is resin fixed to the opposing party wall and the rear dormer floor is now joisted. The rotten fascia board is removed and replaced, and we've hung the eaves tiles back in place. We're almost ready to start building the dormers.